Views: 129 Author: Site Editor Publish Time: 2024-04-22 Origin: Site
Wastewater Type | Industrial wastewater Treatment |
Implementation time | |
Processing scale | 125m3/h |
Project name | Dongtai Bizhiyuan Water Purification Co., Ltd. Capacity Expansion (Phase I) Project |
Product name | RDAF High Efficiency Dissolved Air Flotation |
Process | Fine screen + regulating tank + sand settling tank + flotation tank + hydrolysis acidification tank + combined A/O biochemical tank (biological contact oxidation method) + high-efficiency sedimentation tank + sand filter tank + ozone contact tank |
The project includes seven sewage treatment plants to treat industrial wastewater, using the process of "fine screen + regulating tank + sand settling tank + air flotation tank + hydrolysis acidification tank + combined A/O biochemical tank (biological contact oxidation method) + high-efficiency sedimentation tank + sand filter tank + ozone contact tank.
The influent is township industrial sewage pre-treated by screen sand settling, SS≤ 110 mg/L, TP≤ 6 mg/L. After being treated by air flotation equipment, the effluent indicators meet the following requirements: SS≤ 10 mg/L, TP≤ 1.8 mg/L. The SS removal rate is ≥90%, and the TP removal rate is ≥70%.